| 2025-2026 | Residential security cameras installation |
| 2025-2026 | Interior and Exterior Lighting upgrade to LED |
| 2025-2026 | Sump Pump Replaement in Sprinkler Room and Electrical Room |
| 2025-2026 | Parking Garage ceiling renovation |
| 2025-2026 | Dry sprinkler system replacement |
| 2025-2026 | Hot water heater replacement in sprinkler room |
| 2024-2025 | Asphalt replacement (North and West) |
| 2024-2025 | Parking garage columns, stucco coating repairs |
| 2024-2025 | Epoxy floor painting |
| 2024-2025 | Overhaul MAU #1, #2, and #3 |
| 2024-2025 | Capital Unit Renovations |
| 2024-2025 | Fire Door Replacement and Painting |
| 2024-2025 | Garbage chute rooms renovation |
| 2024-2025 | Thermoscanning (residential units) |
| 2024-2025 | Pedestrian walkway (traffic improvement) |
| 2025-2026 | Interior and Exterior Lighting upgrade to LED |
| 2025-2026 | Terrace Heating Boilers replacement |
| 2025-2026 | Garage Ramp Door Replacement and Surveillance |
| 2024-2025 | Sump Pump Replacement |
| 2024-2025 | Terrace Dual Temperature Pumps |
| 2024-2025 | Generator room renovation |
| 2024-2025 | Epoxy Floor Painting |
| 2024-2025 | Mechanical Room door replacement project |
| 2026 - 2027 | Capital Unit Renovations |
| 2026 - 2027 | EIFS and Window Replacement Phase 2 |
| 2026 - 2027 | Rooftop Unit Replacement and BAS installation |
| 2025-2026 | Intercom Replacemnt |
| 2025-2026 | Make-up Air Unit (MAU) replacement with Condenser (Corridor)(1 unit) |
| 2026-2027 | Parking Level P1 Wall Painting and Door Painting |
| 2026 - 2027 | Linkway Roof Repairs |
| 2026 - 2027 | Actuator replacement, valve, sensors (Fan coil) |
| 2026 - 2027 | Storm and Sanitary connection and Drainage Replacement |
| 2026 - 2027 | Parking Garage - Foundation Walls Repairs (P1 & P2) |